Douglas Parkway Reconstruction – 128th Street to 124th Street Eastbound

Description:

This project will reconstruct the eastbound lanes of Douglas Parkway from 128th Street to 124th Street.

Project Status Update – 05/15/19

The eastbound lanes of Douglas Parkway have been removed.  The Contractor, Iowa Civil Contracting, will prepare the subgrade and then set reinforcing steel prior to pouring the new pavement.  The inside westbound lane of Douglas Parkway will be closed during pouring operations and advance notice will be posted.  The pour is currently scheduled for Saturday May 18; however, it will be pushed back if it rains.  After the main lanes are poured, the turn lanes will be poured, and then several days of cure time are required before the pavement is painted and reopened to traffic.

The contractor is entirely removing and replacing the eastbound lanes.  A detour route is provided. The closure is expected to last approximately three weeks, weather permitting.  We appreciate your patience as we improve this roadway.