104th Reconstruction – Hickman Road to Douglas Ave

Project Description:

This project is the total reconstruction of 104th Street from Hickman Road to Douglas Parkway as a three-lane urban section roadway. This road would have one lane in each direction plus a left turn lane. Storm sewer would be installed with this project to allow the ditches to be filled and curb and gutter used on the new street. Sidewalks will be provided on both sides of 104th Street.

Project Status Update, 08/23/2019:

104th Street is closed to all traffic in Stage 1 from south of Buena Vista Drive to north of the creek crossing (see Road Closure Map and Staging Map below). In the past months, the work by the City Contractor has been significantly delayed due to independent utility relocations and excessive rainfall.

The Contractor, CTI, has completed most of the culvert and storm sewer construction and water main relocation in Stage 1, and has started preparing for paving. Paving is currently scheduled to begin on Tuesday, August 27, weather permitting.

New York Avenue at 104th Street will be closed for the week of August 26th to allow for storm sewer installation.  Storm sewer and water main are being installed ahead of pavement removal in other stages to reduce the duration of future road closures. Weather permitting, Stage 1 will be completed by early September, at which time work will move south to Stage 2.

Please check back to this page for project updates. We appreciate your patience.

Access and Work Zones:

Portions of 104th Street will be completely closed to through traffic during construction. Access will be provided for businesses along the road during road closures. Please follow posted signs and detours for routing around construction.

Check back here for updates on closures as work progresses.