Meredith Drive - 156th Street to 170th Street

Project Description:

This project provides for the reconstruction of Meredith Drive from 156th Street west to ¼ mile east of 170th Street as a four-lane roadway with left turn lanes including grading, and storm sewer. The paving will be portland cement concrete with two 26-foot wide paving sections and a 28-foot grass median and a 10-foot trail on the north side. This is a joint project with the City of Clive. It is anticipated that this project would be completed by the end of November 2019.

Project Status Update - 02/20/19

Concrete Technologies Inc. (CTI), has been hired by the Cities for the reconstruction of Meredith Drive. The project will be completed in 2 major stages and will start with tree removal in both stages in March. As a part of the project, MidAmerican Energy will need to relocate the existing power lines and their contractor will start trimming trees on February 25th.

Stage 1 will consist of reconstructing Meredith Drive from 156th Street to just east of NW 164th Street. It is anticipated the first phase of the project will start in March or April depending on the weather. Meredith Drive will be closed to all through traffic for this work. 160th Street and 162nd Street will be closed at Meredith Drive. A temporary access will be constructed for the Acadia Subdivision to access Meredith Drive. An official detour route will be established on 156th Street, Douglas Parkway and 170th Street. The Police and Fire Departments will be notified of the closed areas.

Once Stage 1 is complete and open to traffic, the road closures will be adjusted for Phase 2’s construction. Phase 2 construction will consist of the closure of Meredith Drive from the west side of 162nd Street to 170th Street.

Helpful Downloads