75th Street & Douglas Avenue Intersection Improvements

Description

This project includes left turn lanes and a new traffic signal at the intersection of 75th Street and Douglas Avenue to increase the capacity of the intersection and reduce travel time through the intersection.

Project Status Update - 7/9/18

The project is anticipated to start on July 16, 2018 and be completed by the end of November 2018.

Prior to the work starting, a representative from the contractor will be passing out additional information and talking with businesses.

The project will be constructed in 3 phases. For all 3 phases, a minimum of one lane for westbound and eastbound traffic will be open for the duration of the project. Please see the Project Phasing Map below.